Harwell site - project update

May 16, 2011

B462 - 104 cans of RH-ILW have been processed this financial year. 

B220 - four cans have been conditioned so far. Waste preparation and resin impregnation has continued within the decommissioning cell.

LETP - HLA - The repaired Flygt mixer has been transferred to B336.10A in preparation for tank mixing.

B551 - Delay Tank - The team is removing pipework from the lower bund and carrying out the electrical soft strip of the pump house.