Harwell site - project update
May 16, 2011
B462 - 104 cans of RH-ILW have been processed this financial year.
B220 - four cans have been conditioned so far. Waste preparation and resin impregnation has continued within the decommissioning cell.
LETP - HLA - The repaired Flygt mixer has been transferred to B336.10A in preparation for tank mixing.
B551 - Delay Tank - The team is removing pipework from the lower bund and carrying out the electrical soft strip of the pump house.